Decatur, Illinois
Summer 2008
Challenge
The existing lot to be replaced was in excess of 20 years
old and in disrepair. A portion of the lot with newer pavement
by Dunn Company needed refinishing. The facility is open 7
days per week; 24-hours per day, so the majority of the lot
had to remain open for employees due to parking needs. The
entire lot had to remain open on weekdays.
Solution
The half-lane rotomill removed existing asphalt at variable
depths to provide a smooth base for the paving surface of
2-inch hot mix asphalt. The work was divided into 5 phases
to allow for employee parking and work was performed on weekends
to maintain parking for employees during week. Milling was
done on Saturdays and paving was done on Sundays. The area
to be worked on that weekend was closed Friday evenings during
shift change.
Construction Phasing
Phase 1: Mill 1 to 2-inch variable depth milling
on West Lot
and Circle Drive. Install 2-inch compacted hot mix asphalt.
Phase 2: Same as phase 1 on northwest portion
of lot.
Phase 3: Same as phase 1 on north portion of
lot.
Phase 4: Same as phase 1 on northeast portion
of lot.
Phase 5: Sealcoat existing pavement with a 1-coat
squeegee and 1-coat spray of coal tar sealant.
Results
- Lot opened during weekdays.
- Minimal disruption to employee parking during weekends.