Decatur, Illinois
Late Fall 2008
Challenge
Dunn Company served as the General Contractor for this large
project. The project called for increased employee and customer
parking capacity by adding a new lot to prepare for expansion
of the hospital building. The project started in Oct.2008
and needed to be completed by Dec.1.It also required the coordination
of five subcontractors to provide proper phasing of work to
meet completion date and minimize the time the parking lot
on the south side of the hospital needed to be closed. Additional
work called for installation of new storm sewer drains and
retention pond on south side of hospital to allow for increase
drainage on the additional lot.
Solution
Pre-project planning and coordinating work between various
subcontractors was essential to keep the tight schedule and
meet the completion deadline of Dec. 1. Subcontractors included
Christy-Foltz, Rainey Landscaping, Bodine Electric, C&J
Excavating, Keeping-it Green, GRS Contracting and Burns Plumbing.
The new parking lot was created with a new drainage and retention
pond and new curbs and gutters with islands throughout the
parking lot.
Construction Phasing
The project was divided into 3 phases, with these
same steps taking place in each phase:
- Demolition, excavation and grading (C&J Excavating)
- Install underground utilities (GRS Contracting on Storm
Sewer) Bodine Electric on underground electrical
- Install curb and gutter (Christy-Foltz)
- Install irrigation (Keeping It Green)
- Install base and asphalt (Dunn Company)
- Install landscaping (Rainey Nursery) and lighting (Bodine
Electric)
Results
- Project was substantially completed by the Dec.1
deadline.
- Minimal disruption to hospital.
- Three-phase project allowed parking to be available to
employees on the south side throughout project.