|


Iroquois County
June, 2008
Challenge
The existing 3.5 miles of 14-foot oil and chip surface had
a minimal aggregate base and was insufficient width for vehicle
to pass without pulling onto shoulder. The strength of the
road was insufficient for regular traffic and truck traffic
from a nearby gravel pit.
County budget constraints and keeping the road open to local
traffic added to the complexity.
Solution
A cross section of the road was widened to allow addition
of three lanes of pavement on either side of the existing
roadway. (This was completed by county work force in fall
2007).
Four inches of crushed aggregate was added on either side
of the existing roadway after ditches were relocated. (This
was completed by county work force in fall 2007).
Pulverized and blended aggregate material was added to the
existing oil and chip surface. The blended material was stabilized
with 10 percent fly ash to a depth of 12 inches and width
of 20 feet.
The road was graded and compacted and a bitumenous cure coat
applied. The roadway was trimmed with a full lane rotomill
using a 30-foot averaging ski with a 2 percent cross slope
was established. The material from trimming was placed as
aggregate shoulders. An A-2 bituminous surface treatment was
applied.
Construction Phasing
Phase 1: Pulverize and blend existing oil and chip
with added base materials—2 days
Phase 2: Incorporate fly ash, grade and
compact—3 days
Phase 3: Curing—7 days
Phase 4: Apply A-2 surface treatment—2
days
Click
here to download the PDF of this project.
|