Challenge
Existing 23-year-old bituminous pavement had extensive cracking,
oxidation and fatigue. The facility is open for business 7
days-a-week with only one entrance and exit. Work needed to
be performed while maintaining loading dock availability.
Work needed to be completed before 9 a.m. in front of auto
service center.
Solution
A portion of the existing concrete driveway median was removed
and the catch basin inlets were repaired. The existing 4-inch
bituminous surface was pulverized and incorporated with the
crushed stone base material. The surface was graded, compacted
and resurfaced with a 2 inch HMA overlay.
Construction Phasing
Phase 1: Remove concrete median, existing asphalt
curbs and repair catch basins.
Phase 2: Pulverize, grade, compact, overlay
and stripe East half of parking lot while coordinating with
service center to keep it open for business.
Phase 3: Repeat Phase 2 on West half of parking
lot.
Phase 4: Install new asphalt curbing, handicap
signage and final clean up.
Results
- Project completed in two work weeks.
- Entire lot was open on weekends.
- Store was open for business with minimal disruption during
the entire project.