|


Various Urban Roadways
Summer 2005
Challenge
Urban streets, built 60 to 80 years ago, were constructed
on substandard bases. These developed exaggerated crowns creating
safety and drainage problems. Curbs and gutters were completely
covered by numerous applications of oil and chip plus patch
work. The streets needed to be reconstructed to regain a realistic
profile, but the Decatur Public Works Department had budget
constraints and a maximum 5 day per section completion schedule.
Solution
Dunn used its state-of-the-art RS-500B Reclaimer/Stablizer,
equipped with on-board programmable micro-processor to control
water distribution and make curing time predictable.
Construction Phasing
Extensive testing for recyclable materials and street coring
was done to determine the composition of the pavement.
Phase I: Pulverize the existing surface and
base to incorporate the materials and utilize what was possible
for base, once all utility structures were lowered.
Phase 2: Use a condensed schedule with multiple
crews completing multiple processes simultaneously.
Phase 3: Use a mill to remove a portion of the excessive
material bringing the street down to a proper slope and grade.
Phase 4: Stabilize the base. The stabilizing agent
was determined and incorporated at a rate of 7 percent by
weight.
Phase 5: After only one day of curing, they were
then able to place a 76.2mm/3 inch material of Class 1 hot
mix asphalt on the new stable and profiled street.
Results
- Project completed in five phases
- Minimal disruption to local traffic
- Met tight budget constraints
- Met 4-day schedule requirement
Project Notes
- The road had a 330.2 to 706.4mm/13 to 16 inch grade change
from curb face to the center line when the standard should
have been about 88.9mm/3.5 inches.
- Productivity and maneuverability of the RS-500 made this
project possible.
- Dunn’s ability to increase power and provide multiple
applications allowed for aggressive completion schedule.
Click here to download the PDF of this project.
|