(Nokomis Road)
Christian County, Illinois
Summer 2006
Challenges
The existing 11.5-mile roadway is a full depth bituminous
pavement with extensive transverse and longitudinal cracking,
rutting and surface oxidation. The average daily traffic is
approximately 3,300 vehicles per day of which 350 to 400 are
loaded trucks from two local limestone quarries. The 11-foot
wide pavement was too narrow for the heavy traffic and maintenance
of the aggregate shoulders was a continuous safety problem.
The location of the quarries made it necessary to keep the
roadway open to traffic during construction.
Solution
Rehabilitate a 2.5-mile section using full depth reclamation
with engineered asphalt emulsion.
The rehabilitation included:
- Removal of the existing aggregate shoulders (3 feet wide
by 10 inches deep) to accommodate 3 feet of additional pavement
width.
- Removal of 2 inches of the existing bituminous pavement
by cold milling and placing the millings in the widening
trench.
- Pulverizing the remainder of the existing 11-foot wide
bituminous pavement (8 to 11 inches) deep.
- Incorporate (3 percent by weight) engineered asphalt emulsion
(Fortress), provided by SEM Materials, to a width of 14
feet.
- Grade and compact then allow to cure until the moisture
content is below 2.5 percent.
- Trim roadway with a full lane width rotomill, using a
30-foot averaging ski, to a cross-slope of 2 percent.
- Place 3.5 inches of HMA in two lifts to a total pavement
width of 28 feet.
- Install 2-foot wide aggregate shoulders using the material
excavated from the widening trench.
- Stripe the lane width back to 11 feet with a 3-foot wide
bituminous safety shoulder and a 2-foot wide aggregate shoulder.
Construction Phasing
Phase 1: Remove aggregate shoulders, perform
2 inches cold milling and place millings in widening trench.
(2 days using a Wirtgen 1900 Combo Cutter for trench removal
and a Wirtgen W-2000 & W-1900 for 2 inch surface removal)
Phase 2: Pulverize remaining bituminous pavement
8 to 11 inches deep. (3 days using two Wirtgen 2500S stabilizers)
Phase 3: Incorporate asphalt emulsion, grade
and compact. (2 days using two Wirtgen 2500S stabilizers and
associated equipment)
Phase 4: Curing. (7 days)
Phase 5: Trimming to final grade and slope.
(2 days using a Wirtgen W-2200)
Phase 6: Place 7000 tons of HMA binder and
surface course. (5 days)
Phase 7: Place 2-foot wide aggregate shoulders.
(1day)
Phase 8: Pavement striping. (1 day by sub
contractor)
Results
- Project completed on time and on budget.
- New pavement structure consisting of 9 inches of emulsion
stabilized base course with a 3.5 HMA asphalt surface capable
of handling 80,000-pound loads.
- Expanded overall pavement width of 28 feet allowing for
a 3-foot safety shoulder on each side of the roadway.
- Extended service life of roadway by using in place materials
which saved money, time and resources.